Road Closure at Muaidher 

Doha: Public Works Authority "Ashghal" closes the one kilometer street extending from Sadeera Street up to the service road parallel to Furousiyya Street at Muaidher, from Monday, 26th April 2010 up to a period of one week. The closure is in order to complete upgrade works including new asphalt pavement on the street, within the project for construction and upgrade of roads works at Muaidher area.

The project includes ground leveling, asphalt pavement, curbstone and footpaths, in addition to road cutting works for other service agencies.  The  project estimated at 26.66 million Qatar Riyals is supposed to be completed by first quarter of the month of May 2010.

 