The work comprises of the Construction of property sewer extension and house connections together with the construction of the necessary sewer network pipe line to connect into the existing network all as described herein. The works are to be carried out to individual/or group of properties at Al Jazeera/ Qatar TV Stations.
The Contractor shall be required to pay charges for Traffic Department of Ministry of Interior as well as “Excavation Permit” charges for Road Opening of Concerned Municipalities and these allowances should be reflected in the prices.
The actual quantities for whole of the Works are subject to re-measurement in accordance with Sub Clauses 55.1 and 55.2 of the Particular Conditions of Contract.
The Contractor shall commence, complete and deliver the whole of the Works within 210 days plus 400 days Maintenance Period.