Refurbishment and upgrading works for various pumping stations – Phase 8 (2)

Brief description
Upgrading of 3 pumping stations: PS17, PS40 & PSW1.

Construction of rising mains for PS 17, PS 40 & PSW1: Total length around 12KM
  1. PS 17- Doha International Airport
  2. PS 40- Al Thumama
  3. PS W1- Al Wakra
Benefits

Enhancement & upgrading works for the infrastructure services are required to address the demands of the nation's growing population, thus providing better drainage services for all communities living in Qatar.

Project Information
Geographical Location N/A
Area Multiple Areas
Sector Drainage Projects
Total Cost 171,142,467 Q.R.
Status Complete
Type Drainage
Start Date 01 July 2011
Expected completion date Third quarter of 2015
Construction company

M/s Petroserv Limited

Consulting company

Parsons International Limited