Al Thakhira Sewage Treatment Works, Transfer Pumping Station & Associated Pipelines

Brief description
Al Thakhira Sewage Treatment Works, once completed will serve a population of about 205,000 with a peak flow of 1,950 liters a second.
Benefits

The project comprises Sewage infrastructure with a daily average flow of 56,200 m3 /day. Sewage transmission mains will comprise 21 km of twin rising mains and approximately 11 km of twin rising mains. Treatment process includes Mechanical Treatment, Biological Nutrient Removal, using Sequencing Batch Reactors (SBRs), Sand Filters and Ultrafiltration, Ultra Violet (UV) disinfection and chlorination system. The treated sewage effluent (TSE) transmission system will consist of about 38km of mains.

A new pumping station to transfer the flows at Al Thakhira and modifications to the existing pumping station at Alkhor are also included in the scope of services.

Project Information
Geographical Location N/A
Area Multiple Areas
Sector Drainage Projects
Total Cost 1,510,955,000 Q.R.
Status Complete
Type Drainage
Start Date 01 March 2015
Construction company
Hyundai Rotem - Aqualia Mace JV
Consulting company N/A