Roads and Infrastructure Development Project in Fareej Al Mawater (Phase 1)

Brief description
The project aims to link Fareej Al Mawater to Rawdat Rashid Road and provide it with the required infrastructure. The new road will serve the stores and workshops that are currently being developed in Fareej Al Mawater project.
Benefits
The new road is 1.8km long and includes 3 lanes in each direction. It starts from the first roundabout on the new Rawdat Rashid Road and surrounds two sides of Al Mawater City. The road includes two signal-controlled intersections to connect to the local roads within the new development of Al Mawater City. The project included the installation of lighting poles, safety barriers, traffic signboards and interlock, as well as the construction of a new electrical substation, and the provision of the essential utilities including water, electricity, telecommunication services.
Project Information
Geographical Location N/A
Area Multiple Areas
Sector Infrastructure Projects
Status Complete
Type Drainage
Start Date 01 April 2017
Expected completion date Third quarter of 2017
Construction company
​“Boom Construction” and “Lotus Trading and Contracting” Joint Venture
Consulting company

AECOM